On December 30, 2023, Liqin Resources OBI Wet Method Phase III ONC project successfully completed the water intake system of the water node, providing a strong guarantee for regional water supply safety and follow-up project construction work.

The overall water intake pipeline of the project is 9.4 kilometers long, the site is busy with traffic, many surrounding obstacles, and the production cable is crossed along the line, making the construction difficult. Under the leadership of the ONC project team, the project has set up a special team of integrated pipe network, and has worked together with professional teams such as China 12th MCC, China 20th MCC, and Shanghai Baoye to overcome numerous difficulties in rigorous investigation, accurate mapping, and safe construction.
This arduous task was finally successfully completed on December 30, 2023, with the successful realization of the production water flow node. This marks the perfect end to the 2023 ONC project and lays a solid foundation for the official production in 2024.