Zhenshi Group Indonesia Yashi No. 2 electric furnace successfully ignited at 16:56 pm on September 2nd! The first electric furnace (4# furnace) invested and constructed by Yashi Indonesia Investment Co., Ltd., a subsidiary of Zhenshi Holding Group, in Weidabey Industrial Park was successfully tapped at 17:18 on June 22, local time.
The first phase of the Yashi project consists of 4 production lines, all located in Indonesia's Vidabe Industrial Park. After full production, it can achieve an annual output of 35,000 tons of nickel metal equivalent. The project officially started on March 15, 2019. It took 15 months to realize the first production line to be put into operation, and then the remaining three production lines will be put into operation one after another.